Hello,
While testing the Gantt, I found an issue with baselines. When a task with a baseline becomes unscheduled, the baseline doesn’t reset correctly.
Here are the cases I found:
Add task → Set baseline → Clear end-date → Set baseline again → Incorrect result.
Add task → Set baseline → Clear start-date, end-date, and duration → Set baseline again → Incorrect result.
Forum post
Hello,
While testing the Gantt, I found an issue with baselines. When a task with a baseline becomes unscheduled, the baseline doesn’t reset correctly.
Here are the cases I found:
Add task → Set baseline → Clear end-date → Set baseline again → Incorrect result.
Add task → Set baseline → Clear start-date, end-date, and duration → Set baseline again → Incorrect result.
I was able to reproduce this issue using your example: https://bryntum.com/products/gantt/examples/baselines/.
Here’s a video demonstrating the issue:
Baseline.issue.mp4
Thank you, Luca.