Reword sensitivity analysis description of inflation costs during construction to characterize the min/max range for the min/max stimulation cost adjustment factors; previous description was using values for a single stimulation cost factor.
Copy file name to clipboardExpand all lines: docs/Fervo_Project_Cape-4.md
+1-1Lines changed: 1 addition & 1 deletion
Display the source diff
Display the rich diff
Original file line number
Diff line number
Diff line change
@@ -112,7 +112,7 @@ sensitivity analysis using [GEOPHIRES's Monte Carlo simulation module](Monte-Car
112
112
113
113
The following tables and heatmaps show Electricity breakeven price (LCOE) and NPV sensitivity to stimulation cost and inflation costs during construction (a proxy for construction delays and cost overruns).
114
114
Stimulation costs were tested from $2.3M/well (Reservoir Stimulation Capital Cost Adjustment Factor = 0.5) to $9.2M/well (Reservoir Stimulation Capital Cost Adjustment Factor = 2).
115
-
Construction inflation costs were tested from $53.58M (Inflation Rate During Construction = 2.3%) to $340.13M (Inflation Rate During Construction = 14.6%).
115
+
Inflation Rate During Construction was tested from 2.3% to 14.6%, yielding construction inflation costs ranging from $53.6M to $459M.