Project Management - PERT/GANTT/WBS
It is intended with the project of this unit that the students create the documentation to support the management of a software project. The main objective of the unit is to enable controlled monitoring of the implementation project.
To implement the project the student should consider that you have 3 computer engineers at a cost Man / Hour of 120 euros / hour and a Project Manager at 150 euros / hour. This already includes all office expenses, subsidies and equipment. The Manager is 50% interested in this project. Here's the list of items to include in the report:
-
Hierarchical tree of modules. With Times per task / day (8 hours)
-
Budget analysis. They only consider receiving the last 40% of the money in the second year because it is a funded project and the remaining payment comes one year after the start. CachFlow map considering that 3 desktop computers have to be purchased. Price / Computer 2000 euros.
-
Map PERT and respective analysis of times of activities. (Durations have to be calculated previously based on optimistic and pessimistic and common but do not consider critical chain) - Map must have LST, LFT, LSS, EFT put in the MAP with the square brackets.
-
Correct PERT to place dependencies between activities considering Resources. (We want dependencies on activities of the same resources, put activities of name buffer with 50% size of each activity, only in the critical path, critical path that was affected by the dependencies caused by the resources)
-
1 Activity Report and 1 Simulated Progress Report in the middle of TD. You must have at least one overdue activity and one with overtime.